The methodology of the project is consisted with the following ten work packages
to ensure the accomplishment of the objectives of THREE-LANKA project.
Training Hub for Renewable Energy Technologies in Sri Lanka.Expand All
1.1 | Conduct a survey of the renewable energy related modules and courses in SL HEI and its underpinning modules and or activities . | |
Assigned Date: 2022-09-29 Start Date:2021-01-16 | End Date:2021-04-15 |
1.2 | Conduct a survey of the renewable energy modules in EU partners institutions at FE and HE and its underpinning modules and or activities . | |
This task is Completed. Assigned Date:2021-01-15 Start Date:2021-01-15 | End Date:2021-04-15 |
1.3 | Conduct a survey of the renewable energy training centres in EU partners including infrastructure and activities . | |
This task is Completed. Assigned Date:2021-01-15 Start Date:2021-01-15 | End Date:2021-04-15 |
1.4 | Document differences in theoretical and practical training between Sri Lanka and the EU, to demonstrate the benefit of the THREE-LANKA cross-disciplinary energy related curriculum . | |
This task is Completed. Assigned Date:2021-01-15 Start Date:2021-01-15 | End Date:2021-04-15 |
1.5 | Identify possible developments to harmonise Sri Lanka and EU education . | |
This task is Completed. Assigned Date:2021-01-15 Start Date:2021-01-15 | End Date:2021-07-15 |
1.6 | Name Member for Review of the WP1 Report . | |
This task is Completed. Assigned Date:2021-01-26 Start Date:2021-07-03 | End Date:2021-07-05 |
2.1 | Design programmes and develop learning outcomes. | |
This task is Completed. Assigned Date:2021-04-15 Start Date:2021-04-15 | End Date:2021-09-15 |
2.2 | Design the training track A & its ILO's. | |
This task is Completed. Assigned Date:2021-04-15 Start Date:2021-04-15 | End Date:2021-09-28 |
2.3 | Design the training track B & its ILO's. | |
This task is Completed. Assigned Date:2021-04-15 Start Date:2021-04-15 | End Date:2021-09-28 |
2.4 | Design the training track C & its ILO's. | |
This task is Completed. Assigned Date:2021-04-15 Start Date:2021-04-15 | End Date:2021-09-28 |
2.5 | Develop core modules for RE-Tech track A. | |
Assigned Date:2021-08-29 Start Date:2021-10-01 | End Date:2022-06-01 |
2.6 | Develop core modules for RE-Eng track B. | |
Assigned Date:2021-08-29 Start Date:2021-10-01 | End Date:2022-06-01 |
2.7 | Develop core modules for RE-PM track C. | |
Assigned Date:2021-08-29 Start Date:2021-10-01 | End Date:2022-06-01 |
3.1 | Develop supporting modules for RE-Tech track A with Virtual lab facilities. | |
Assigned Date: 2021-08-29 Start Date:2021-10-15 | End Date:2022-04-15 |
3.2 | Develop supporting modules for RE-Eng track B with virtual lab facilites. | |
Start Date:2021-10-15 | End Date:2022-12-04 |
3.3 | Develop supporting modules for RE-PM track C. | |
Start Date:2021-10-15 | End Date:2022-12-04 |
3.4 | Development of Remote Labs . | |
Assigned Date: 2022-09-25 Start Date:2022-09-26 | End Date:2022-11-30 |
3.5 | Prepration of vertial labs. | |
Assigned Date: 2022-09-25 Start Date:2022-09-25 | End Date:2022-09-30 |
4.1 | Develop the E-Learning guidelines, templates and instructions. | |
Start Date:2021-10-15 | End Date:2022-02-15 |
4.2 | Develop E-Materials for all tracks. | |
Start Date:2021-10-15 | End Date:2023-01-15 |
5.1 | Design/establishment of the HUB infrastructure/ hierarchy & bylaws. | |
Start Date:2021-10-15 | End Date:2022-02-15 |
5.2 | Define and prepare the hard-software tools’ specifications and bid documents. | |
Assigned Date: 2021-08-29 Start Date:2021-08-30 | End Date:2021-11-15 |
5.3 | Define and prepare H/SW tools’ specifications and bid documents/ purchase/installation. | |
Start Date:2021-10-15 | End Date:2022-02-15 |
5.4 | Development of the resources and experiments/verification. | |
Start Date:2021-10-15 | End Date:2022-02-15 |
6.1 | Establish the criteria of EG trainers selection. | |
Start Date:2021-03-15 | End Date:2022-05-15 |
6.2 | Training of EG trainers. | |
Start Date:2021-03-15 | End Date:2023-05-15 |
6.3 | Feedback from EG trainers, evaluation of the training course. | |
Start Date:2021-03-15 | End Date:2023-05-15 |
6.4 | Feedback from EU partners on EG trainers. | |
Start Date:2021-03-15 | End Date:2023-05-15 |
7.1 | Processing the EG recognition/accreditation. | |
Start Date:2021-10-15 | End Date:2023-03-15 |
7.2 | Processing the EU recognition/accreditation. | |
Start Date:2021-10-15 | End Date:2023-03-15 |
7.3 | Implementation at RE-Tech level. | |
Start Date:2021-10-15 | End Date:2022-11-15 |
7.4 | Implementation at RE-Eng level. | |
Start Date:2021-10-15 | End Date:2022-11-15 |
7.5 | Implementation at RE-PM level. | |
Start Date:2021-10-15 | End Date:2022-11-15 |
8.1 | Monitoring activities and outcomes. | |
Start Date:2021-01-15 | End Date:2023-01-14 |
8.2 | Quality Assurance. | |
Start Date:2021-01-15 | End Date:2023-01-14 |
9.1 | Holding workshops and seminars. | |
Start Date:2021-01-15 | End Date:2023-01-14 |
9.2 | Activates related to advertisement and outreach campaign. | |
Start Date:2021-01-15 | End Date:2023-01-14 |
9.3 | Outreach activities for marketing for the training programmes. | |
Start Date:2021-01-15 | End Date:2023-01-14 |
9.4 | Integration with national training schemes & Sri Lankan programmes for workforce development. | |
Start Date:2021-01-15 | End Date:2023-01-14 |
10.1 | Coordinator establishes all-together meetings every 6 months.. | |
Start Date:2021-01-15 | End Date:2024-01-14 |
10.2 | Coordinator ensures adhesion to project regulations and all activities and expenditures are compliant to the EU guidelines.. | |
Start Date:2021-01-15 | End Date:2024-01-14 |
10.3 | WP leads agree the involvement of each partner in their WP and initiate a follow up virtual and physical meetings every month.. | |
Start Date:2021-01-15 | End Date:2024-01-14 |
10.4 | All partners representatives and WP leads agreeing on any amendments to the initial project plan with full endorsement from the EU.. | |
Start Date:2021-01-15 | End Date:2024-01-14 |
10.5 | Follow up on a regular basis with regard to the WP progression. | |
Start Date:2021-01-15 | End Date:2024-01-14 |
10.6 | UoR as coordinator should communicate all requests and reports to the funding body main office.. | |
Start Date:2021-01-15 | End Date:2024-01-14 |